Environmental Project Log: Kenilworth DFD #002B2Q
Status on May 23, 2002, after final cleaning, visual inspection and clearance air test.
| View of ash pits (unguarded floor hazard) and unguarded opening to basement (right of stairs). These hazards must be abated before this area is re-occupied. |
 |
Mezzanine requires guardrail modification before area may be reoccupied. |
Project status as of May 24, 2002:
- The containment received final cleaning and powerwashing the week of May 20th.
- Visual and clearance air monitoring performed by Skyline Industrial Safety and Occupational Health (5/24/2002). Test results were less than 0.002 f/cc (i.e., passed).
- Some minor work still required, including demolition of metal stud/sheetrock wall (by abatement company), as well as guardrail/fall protection modifications to this area (by PPS).
- The stack must still be inspected by Mark Kazmierski; the ash-cleanout was the responsibility of the abatement company.
Please see the Kenilworth Index Page and Project Log for additional information.